国家重点建设项目管理办法 MEASURES FOR THE ADMINISTRATION OF NATIONAL KEY CONSTRUCTION PROJECTS

2006-05-15 23:15   我要纠错 | 打印 | 收藏 | | |

计建设(1996)1105号
(Approved by the State Council on June 3, 1996 and promulgated by the State Planning Commission on June 14,1996)
颁布日期:19960614  实施日期:19960614  颁布单位:国家计委

  Article 1 These Measures are formulated for the purposes of strengthening the administration of national key construction projects, ensuring the construction quality and that the projects are completed on time, enhancing the investment returns and promoting the sustained, rapid and healthy development of national economy.

  Article 2 “National key construction projects” referred to in these Measures mean key construction items which are selected from the following large- and medium-sized national capital construction projects because of great influence upon national economy and social development:

  (1) large-sized items of infrastructure, basic industries and pillar industries;

  (2) items of high technology which can promote the industrial technological progress;

  (3) transregional items of great influence upon national or regional economic development;

  (4) items of great influence upon social development; and(5) other key construction items.

  Article 3 National key construction projects shall be designated in accordance with the national industrial policies, based upon the necessity and impossibility of national economy and social development, and in line with the principle of laying emphasis on priorities, acting according to the capability, leaving some margin, preventing scattered investment and ensuring capital injection and supply.

  Article 4 The planning department under the State Council shall designate national key construction projects in consultation with the competent departments concerned under the State Council.

  Article 5 Planning departments of people's governments of provinces, autonomous regions and municipalities directly under the central government and of cities separately listed in planning, and the competent departments (or companies) under the State Council may, within the scope of items specified in Article 2 and in accordance with the principle in Article 3 of these Measures, balance capital construction items within their respective regions or departments and file with the planning department under the State Council applications for listing some of them as national key construction projects for each year.

  The planning department under the State Council shall, after receiving the applications, seek the opinions of the competent departments concerned under the State Council, make overall balancing and designate preparatory national key construction projects after feasibility study reports of construction items submitted in applications have been approved. National key construction projects shall be designated officially after the construction of items submitted in applications has been started.

  The planning department under the State Council shall publish national key construction projects and preparatory national key construction projects after designating them.

  Article 6 The planning department under the State Council and planning departments of local people's governments concerned shall arrange annual investment plans for national key construction projects according to their construction periods of time.

  Article 7 A legal person established for a national key construction project shall assume overall responsibility for the construction project. If otherwise provided by state provisions, such provisions shall apply.

  A legal person established for a national key construction project shall be in charge of making preparations, raising funds, building, production and business operations, paying off debts and maintaining and increasing the value of assets for the construction project, and shall keep control over funds, time limit, quality and production safety of the national key construction project strictly according to relevant state provisions.

  The Company Law of the People's Republic of China and other relevant state provisions shall be applicable to the organizational form and structure of legal persons established for construction projects.

  Article 8 The competent departments concerned under the State Council, local people's governments concerned, banks, enterprises and institutions, each of whom is responsible for allocations to national key construction projects under annual investment plans and contracts for construction projects, shall ensure the construction allocations according to the schedules of the projects.

  Article 9 Each bank and department concerned shall give priority to equipment reserve allocations to national key construction projects.

  Article 10 The planning department under the State Council and planning departments of local people's governments concerned shall set aside a certain percentage of funds to meet special requirements arising in the process of construction when arranging annual investment plans for national key construction projects.

  Article 11 No unit or individual may misappropriate or retain construction funds and equipment reserve funds for national key construction projects.

  Article 12 Local people's governments shall coordinate the work related to the requisition of land for national key construction projects and shall provide conveniences necessary for the construction. Land administration departments shall ensure the use of land for national key construction projects according to law.

  Article 13 Open tenders shall be invited for the design, construction, management and equipment purchase in the principle part of a national key construction project by the legal person established for the project and the proper tender shall be accepted on the basis of competitive selection, with the exception of those projects for which tender invitations may, with an approval, be negotiated or limited to special persons.

  Grade A (or first-class) qualification specified by the state shall be required for tenderers for national key construction projects.

  Without the consent of the legal person established for the national key construction project, any party having won the tender may not subcontract the construction.

  The planning department under the State Council shall, in consultation with the competent departments concerned under the State Council, local people's governments concerned and banks, exercise the supervision and inspection over the tendering for national key construction projects.

  Article 14 Departments in charge of electric power, transportation, post and telecommunications, water and heat supply shall give priority to electricity for construction and production use, materials transportation, communication, and demand for water and heat required by national key construction projects, and shall perform their duties according to contract.

  Article 15 Enterprises and institutions concerned shall give priority to the supply of equipment and materials required by national key construction projects, and shall perform their duties according to contract.

  Article 16 No unit or person may collect fees from national key construction projects. If otherwise provided by law or by the State Council, such provisions shall apply.

  Article 17 A legal person established for national key construction project shall submit a report on the construction and materials regarding the project to the planning department under the State Council according to relevant provisions and shall send copies of them to the competent departments concerned and the bank.

  Article 18 A project directly supporting a national key construction project shall be put into operation simultaneously with the schedule of the national key construction project. Departments and units financing the construction of such a supporting project shall ensure allocations to it according to the construction schedule.

  Article 19 A legal person established for a national key construction project shall promptly organize the preliminary inspection and acceptance together with the designer and the constructor according to the approved design document and other relevant documents after the completion and trial operation of the project.

  If the project passes the preliminary inspection and acceptance, the planning department under the State Council or an agency authorized by it shall organize the inspection and acceptance upon completion together with involved parties.

  Article 20 A national key construction project which has passed the inspection and acceptance upon completion and has been put into operation shall be given an evaluation upon completion according to relevant state provisions.

  Article 21 The planning department under the State Council shall, in consultation with the competent departments concerned under the State Council and local people's governments concerned, coordinate, guide and supervise the work for national key construction projects.

  Article 22 If any party concerned fails to allocate funds to a national key construction project according to provisions, the planning department under the State Council shall issue a circular to criticize him and propose to the competent department for imposing disciplinary sanction according to law upon the person in charge directly responsible or other persons responsible. If a local investment is not allocated according to provisions for two consecutive years, the planning department under the State Council has the authority to suspend the approval of any new construction project in the locality for the next year.

  If any party concerned fails to allocate funds to a national key construction project according to contract, he shall bear the liability for breach of contract.

  Article 23 If anyone misappropriates or retains funds for national key construction projects, the auditing and financial authorities shall reclaim the funds misappropriated or retained, issue a circular to criticize him and propose to the competent department for imposing disciplinary sanction according to law upon the person in charge directly responsible and other persons responsible; if a crime has been constituted, the offender shall be investigated for criminal liability.

  Article 24 If anyone disturbs the order of the construction and production and business operations of national key construction projects, making it impossible for the work to be conducted normally, he shall be punished according to the provisions of the Regulations of the People's Republic of China on Administrative Penalties for Public Security; if a crime has been constituted, criminal liability shall be investigated according to law.

  Article 25 If a national key construction project costs quite beyond its estimated budget, or has inferior quality, or suffers loss and waste or a liability accident, as a result of poor management or fraud, the planning department under the State Council shall circulate a notice of criticism and propose to the competent department for imposing disciplinary sanction according to law upon the person in charge directly responsible and other persons responsible; if a crime has been constituted, criminal liability shall be investigated according to law.

  Article 26 These Measures comes into effect on the date of promulgation.

相关资讯:
网站导航:
 四六级 指南 动态 经验 试题 资料  托福 指南 动态 经验 留学 备考
 雅思 指南 动态 机经 经验 辅导  公共英语 指南 动态 备考 试题 辅导
 日语 就业 辅导 留学 考试 报考  法语 资料 文化 考试 留学 辅导
 韩语 入门 口语 阅读 留学 文化  西语 辅导 资料 考试 留学 风采
基础法律英语
350元/门
系统讲解知识,全面提升水平
课时数:18课时左右

外语教育网(www.for68.com)是北京东大正保科技有限公司(CDEL)旗下一家大型外语远程教育网站,正保科技成立于2005年7月,是国内超大型外语远程教育基地,上榜“北京优质教育资源榜”--“百万读者推崇的网络教育机构”。


公司凭借雄厚的师资力量、先进的网络视频多媒体课件技术、严谨细致的教学作风、灵活多样的教学方式,为学员提供完整、优化的外语课程,既打破了传统面授的诸多限制,发挥了网络教育的优势,也兼顾面授的答疑与互动特点,为我国培养了大量优秀的外语人才。


为了满足学员学习不同语种、不同阶段的学习需求,网站开设了包括考试英语、行业英语、实用口语以及小语种在内的百余门语言学习课程,涵盖英语、日语、韩语、俄语、德语、法语、西班牙语、意大利语、阿拉伯语等主要语种,供学员自由选择。此外,网站还拥有各类外语专业信息和考试信息20余万条,是广大学员了解外语类考试最新政策、动态及参加各语种培训的优质网站。


北京东大正保科技有限公司成立于2000年,是一家具备网络教育资质、经教育部批准开展远程教育的专业公司,为北京市高新技术企业、中国十大教育集团、联合国教科文组织技术与职业教育培训在中国的唯一试点项目。


公司下属13家行业远程教育网站,业务涵盖了会计、法律、医学、建设、自考、成考、考研、中小学、外语、信息技术、汉语言教学等诸多领域,拥有办公面积8000多平米,员工近千人,公司年招生规模达270万人。由于正保远程教育(China Distance Education Holdings Ltd., CDEL)在中国互联网远程教育行业内的绝对优势和强大影响力,正保教育模式一直被广大投资人所追捧。2008年7月30日,公司在美国纽约证券交易所正式挂牌上市(股票交易代码:DL),是2008年唯一一家在美国纽交所上市的专业从事互联网远程教育的中国企业。


版权声明
   1、凡本网注明 “来源:外语教育网”的所有作品,版权均属外语教育网所有,未经本网授权不得转载、链接、转贴或以其他方式使用;已经本网授权的,应在授权范围内使用,且必须注明“来源:外语教育网”。违反上述声明者,本网将追究其法律责任。
  2、本网部分资料为网上搜集转载,均尽力标明作者和出处。对于本网刊载作品涉及版权等问题的,请作者与本网站联系,本网站核实确认后会尽快予以处理。
  本网转载之作品,并不意味着认同该作品的观点或真实性。如其他媒体、网站或个人转载使用,请与著作权人联系,并自负法律责任。
  3、本网站欢迎积极投稿
  4、联系方式:
编辑信箱:for68@chinaacc.com
电话:010-82319999-2371